Autumn 2026

We made a hole in the roof to locate the east end tank. A couple of near misses, then we found the correct location. In the past, the hole had been covered over with (rather nasty) plywood after the tank entry had been hammered in on itself. Removing the hammered in threaded tube proved a challenge but we got there eventually, cleaned up the remaining bore fit to take the new filler turret.


The filler pipes were modified a little to fit the west end tank and this was subsequently filled to test for leaks and for functioning of the flush tank in the toilet. After testing the tank was emptied as winter weather was looming.


A new east end turret was fashioned from some underground drainage components which were very close to the same diameter as the tank top entry. Before fitting, the tank was vacuumed out to clear a lot of dust, scale and rust. Then the outlet pipes in the toilet were closed off and the tank filled with water to test for leaks. It was fine! The turret was then sealed into the filler hole and left to set completely before filler pipe attachment.

Drop plates were fitted to both gangways and (probably) temporary threshold plates fitted to protect the junction between the internal floor covering and the drop plates. Gangway diaphragms were ordered at this stage.
Please don't forget the Gresley TK appeal - every penny counts!